DurbarSquare Nepal 2007 Charity Project Budget Outline

The budget outline presented below indicates estimated financial range of the project. Certain expenses are based on market research assumptions, therefore an error margin of 10% has been included.

Almost 30% of the total costs will be covered by the organizers.

Unless stated otherwise, all expenses are given in US dollars.
Detailed budget breakdown is available to our partners upon request.

 

1 Aid (medical, educational, sport + handling)
7000
2 Preparation
5265
3 Transport
3300
  Subtotal
15565
   
4 Unforseen costs 10% of actual expenditure
1556,5
  Total
17121,5
   
Covered by Child and Environment:
4539
To be fundraised
12582,5